| Swing bridge 49, Royal Oak, Oakgrove  Royal
            Oak swivel bridge no.49 was one of 13 originally built across the
            canal. Most were famers' accommodation bridges, joining divided fields
            in the same ownership. Royal Oak was the only swivel bridge to carry
            a public highway, and still does. The bridge has had at least three
            incarnations. What we believe to have been the original deck served
            for c.145 years and required replacement in 1973. We have many pictures
            of the works taken at this time showing the construction of
            the original bridge (above) and the new bridge, and also the progress
            of the work.
 
 
                
                  | 
 The original turntable bearing[1]  |  
                  | 
 The original bridge just prior to demolition,
                      particularly showing one of two cast iron pillars with
                      wheel on top carrying the bridge support stays[2]  |  
                  | 
 Showing the then (1973) BW standard
                      pintle prior to installation[3]  |  Notes very kindly submitted by John Powell, retired British
                    Waterways Bridge Engineer.  The casting [top right] for the Royal Oak Swing Bridge
                  No.49 is massive compared with the original drawing for Bridge
                  No.47, I presume problems with strength had been experienced
                  at some time in the past and measures taken to improve matters?  The picture [centre right] shows the Cast Iron King
                  Post with wheel which would have been as originally built,
                  the chain going over the wheel on the original drawing for
                  Bridge No.47 is only about 6 inches long, so it is in all probabilty
                  there, but difficult to see on the photograph.  The 1973 reconstruction of Royal Oak was undertaken
                  by R.J. Russell & Co. Ltd., Civil Engineering Contractors,
                  for the sum of £13,461.00 and I can confirm that the
                  pintle shown in your photograph [bottom right] is the standard
                  BW pintle being used at that time. It had been improved over
                  the old cannon ball pintle [top right] by the incorporation
                  of the vertical post which sits between two transverse beams
                  with a collar assembly fixing the post firmly to the deck.  The vertical post can now transfer any horizontal forces from
                  either traffic braking on the deck or boats hitting the side
                  of the bridge, when previously these forces could only be taken
                  by friction and resulted in deck movement.  Unfortunately this pintle was unable to cope with the rotational
                  movement of the bridge beams under modern day traffic loading
                  and it eventually was replaced with a new pintle with a
                  single block with a domed upper surface, this was undertaken
                  in 1986 and the opportunity was taken to power operate the
                  bridge. This resulted in a conflict between boaters and road
                  traffic and in 1988 Road Barriers were added in the interest
                  of public safety.  
 Bridge 49, Royal Oak, is heavily used by road traffic and
                  has been fitted with a new deck - timber base with modern wearing
                  surface - in January 2012. Operation is electro-hydraulic and carried out by the boater
                  using the CRT key in the adjacent control box. The controls
                  require the presence of the operator throughout the process
                  which can take up to ten minutes. The operator should ensure
                  the boat is approaching the bridge before operation which will
                  begin by lowering the road barriers and closing the highway
                  to vehicular traffic. This is followed by the hydraulic removal
                  of the support wedges from beneath the bridge. Only then will
                  the bridge swing. It will automatically stop when it reaches
                  the fully open position. Once the boat or boats have passed
                  through, the close button is depressed and the above process
                  is reversed. When the barriers are fully up, permitting traffic
                  flow to resume, the key may be removed from the control panel.  
 Acknowledgement
            John Powell, archive research. John is a retired BW Engineer.  Pictures1  Macclesfield
								Canal Society Heapy collection  2  Macclesfield
								Canal Society Heapy collection  3  Macclesfield
								Canal Society collection  |