Bridge 26A, Clarence Mill footbridge, weeks
10-13 |
Week 13 |
11
August - The handrails have arrived and are being installed on
the Clarence side. When completed they will be along both sides
of the ramps and the stairs. They are presently galvanised but
will be painted black to comply with British Waterway's requirements. |
Week 12 |
7
August - A specialist paviour has almost completed laying the
excellently coloured rough surfaced paving stones on the Clarence
Road side. This is the finished surface we shall walk on.
Only the coping stones and hand rails and needed to finish
the construction on this side. |
7
August - On the towpath side the stone facing is almost complete,
the coping stones are being finished off. The screeding and paving
remain to be done next week.
The ground has been landscaped after this picture was taken
by back filling almost to the top of the near wall with soil.
Nature will very soon re-take this area. |
7
August - Roy pointing the undersides of the coping stones. |
Week 11 |
31
July - Time was lost to rain this week. The Clarence Road side
had its walking surfaces screeded in preparation for paving. |
Week 10 |
24
July - The towpath side ramps well under way and the stone facing
almost up. |
24
July - Roy and Dave working on the top of the stone facing. |
Earlier weeks' pictures are here. |
|
|